How to replace the flow cell on a TUV/PDA - WKB295516
Article number: 295516
OBJECTIVE or GOAL
Replace the flow cell on a TUV/PDA.
ENVIRONMENT
- ACQUITY Premier PDA
- ACQUITY Premier TUV
- ACQUITY TUV
- ACQUITY PDA
PROCEDURE
- Turn off the lamp.
- Remove the connection with the green mark.
- Remove the tubing from inlet and outlet (blue circles).
- Loosen the three screws (red marking). They cannot be removed.
- Replace the flow cell.
- Flush the flow cell with organic (e.g., ACN) for a minimum of 15 minutes.
- Power-on the lamp, let it warm up, and then calibrate.
ADDITIONAL INFORMATION
id295516, A-30PDA, A-30UV, UPAPDA, UPARPPDA, UPARPTUV, UPC2PDA, UPPDA, UPPDAARC, UPPDAARCB, UPPDA-E, UPPDA-L, UPPDALTC, UPPDATC, UPPPDA, UPPSMFL, UPPTUV, UPTUV, UPTUVARC, UPTUVARCB, UPTUV-E, UPTUVTC