Skip to main content
Waters

How to reboot the electronics of a Xevo TQ MS, Xevo TQ-S, or Xevo TQ-XS - WKB822

Article number: 822

OBJECTIVE or GOAL

Reboot the electronics on a Xevo TQ MS, Xevo TQ-S or Xevo TQ-XS

ENVIRONMENT

  • MassLynx 4.1
  • Massynx 4.2
  • Xevo TQ-S
  • Xevo TQ MS
  • Xevo TQ-XS

PROCEDURE

(Video below)

  1. Exit MassLynx.
  2. Remove all modules from the DHCP server.
  3. Power off the UPLC stack.
  4. Go to the back of the MS; at the bottom-middle, you will see two toggle switches.
  5. If the system is pumped down, flip the top switch down. This step must be done before the following step. If the system is vented, then this step is not required. If the rough pumps are vibrating, the system is pumped down.
  6. Flip the bottom switch down.
  7. Reboot the PC.
  8. Log back into the PC.
  9. Launch the DPCH server.
  10. Power on the Sample Manager (or the Column Manager, depending on which modules incorporate the ethernet switch).
  11. Wait the Sample Manager to appear on the DPCH server.
  12. Power on one by one all remaining UPLC modules and wait until they re-populate the DHCP server 
  13. Go to the back of the MS and flip only the bottom switch up.
  14. Wait 5 minutes.
  15. Open MassLynx.
  16. Ensure that the vacuum readings are "real" and that everything is communicating properly.
  17. If the vacuum readings are not real (all of them are maxed out to the left), repeat the above procedure. If the vacuum readings are good, flip the top switch on the back of the MS back to the up position to take the system out of pump override.
  18. Put the MS into Operate and confirm functionality.
     

 

ADDITIONAL INFORMATION

 