OBJECTIVE or GOAL

How do I compare or overlay data in Empower from two subprojects within the same parent project?

ENVIRONMENT

  • Empower 2
  • Empower 3

PROCEDURE

  1. Login to Empower.
  2. Click Configure the System.
  3. Select the project of interest by clickingh the + sign next to it to display the subprojects.
  4. Press CTRL key and click on subprojects to highlight them.
  5. Right-click the subprojects and click Open. This opens the projects in Global Projects View.
  6. Click the Channels tab.
  7. Highlight the channels of choice.
  8. Right-click and select Compare.