Does changing Empower project options translate into system policies? - WKB66287
Article number: 66287
ENVIRONMENT
- Empower
ANSWER
No, when an enabled option is changed for a project, it changes the enabled options for that one project. If "copy to sub-projects" is selected, it copies to other projects. It does not change an overall system policy.
ADDITIONAL INFORMATION
If an enabled option is changed, it logs in the system audit trail as a project modification.