Background Processing of Samples currently Acquiring Produces Results with I18 code and Processing Time Stamps before Acquistion Completion Time - WKB65981

Article number: 65981

ENVIRONMENT

  • Empower (Pre SR3)
  • Does not apply to Empower 3 SR3

ANSWER

Prior to SR3 Empower allowed the background processing of data which was currently being acquired. This causes empty or incomplete results. The full chromatogram was available once acquisition had finished.

The results created by this process had a processing time stamp earlier than the acquisition completion time stamp and were also given the I18 integration code indicating the result was created by processing a partial injection.

In SR3 and above Empower prevents background processing of data in channels that are still being acquired. The message center informs the user that background processing for these channels cannot continue.

ADDITIONAL INFORMATION

PCS 53031, 53546 and 55839

https://www.waters.com/waters/support.htm?lid=53031&type=SUGG

id65981, EMP2LIC, EMP2OPT, EMP2SW, EMP3GC, EMP3LIC, EMP3OPT, EMP3SW, EMPGC, EMPGPC, EMPLIC, EMPOWER2, EMPOWER3, EMPSW, SUP

Not able to find a solution? Click here to request help.