In Empower, how can I check system pressure on an Alliance 2695 after a run is completed? - WKB2879
Article number: 2879
OBJECTIVE or GOAL
Check/collect system pressure on an Alliance 2695 in Empower.
ENVIRONMENT
- 2695 Separations Module
- Alliance
- Empower
PROCEDURE
- Click on Browse Projects in Empower.
- Select your project and open it.
- Click on the Methods tab in the Project window.
- Highlight the instrument method and click on the Channel tab (see screen shot below).
- Is System Pressure enabled? If not, you cannot see system pressure.
- If it is enabled, you can see the pressure trace on an ongoing run in a second window via Run Samples.
- If the run has finished, you can check the pressure trace by clicking on the Channel tab in the Project window.
ADDITIONAL INFORMATION
id2879, 2690, 2690D, 2690DUPGD, 2690UP, 2695, 2695D, 2695DE, 2695DEB, 2695DUP, 2695E, 2695EB, 2695INERT, 2695UP, A-10SSM, ALLCOLCLR, ALLCOLHTR, ALLCOLHTRB, EMP2LIC, EMP2OPT, EMP2SW, EMP3GC, EMP3LIC, EMP3OPT, EMP3SW, EMPGC, EMPGPC, EMPLIC, EMPOWER2, EMPOWER3, EMPSW, SUP