OBJECTIVE or GOAL

With Empower, calculate Amount/Concentration, Calibration Curve fit types, and review Fifth Order Fit.

ENVIRONMENT

  • Empower
  • Empower Tip of the Week #283

PROCEDURE

STEP 1
For a Fifth Order Fit, Empower performs a least-squares fit of a fifth-order polynomial to the calibration points. This fit cannot be performed with less than 6 points, and 8 is recommended (Figure 1).
Figure_1.png

STEP 2
The Fifth Order Fit generates a Calibration Curve that is represented by the equation in Figure 2. In this example, a GPC Processing Method was used for a 15-point Calibration Curve (Figure 2).
Figure_2.png 

STEP 3
Calibration Curves can be accessed in various ways, for example:

  1. Review – bring a result into Review and click on the Calibration Curve tool
  2. Compare – right-click on a curve from the Curves tab in the project and select Compare
     

ADDITIONAL INFORMATION

This can be done with either the Pro or QuickStart interface.

Not able to find a solution? Click here to request help.