How to save an old version of a method as the current one in Empower or Breeze - WKB3579
Article number: 3579
OBJECTIVE or GOAL
Save an old version of a method as the current one.
ENVIRONMENT
- Empower
- Breeze
PROCEDURE
- For Empower, Open Browse Project. For Breeze, Find data.
- Click the Methods tab.
- Locate the method you want to change.
- Right-click and choose Method Properties.
- Select the version of the method you want to save as current.
- Click Save As Current.
ADDITIONAL INFORMATION
id3579, BREEZESW, EMP2LIC, EMP2OPT, EMP2SW, EMP3GC, EMP3LIC, EMP3OPT, EMP3SW, EMPGC, EMPGPC, EMPLIC, EMPOWER2, EMPOWER3, EMPSW, SUP, SUPBZ