SYMPTOMS

  • After the GPC license was installed, more than 2000 non-GPC projects have the GPC option enabled in Project Properties
  • Cannot disable the option for the projects without manually clearing it in Project Properties
  • There is no audit trail entry logged when the GPC license activation enables the GPC option for random projects whether they are locked or unlocked projects.

ENVIRONMENT

  • Empower 3 Feature Releases (FR2, FR3, FR4, FR5,) Enterprise / client server

CAUSE

Defect - PCS 54503, CRI-601

FIX or WORKAROUND

Fixed in Empower 3.8.0

ADDITIONAL INFORMATION

Abstract / Summary of Defect

Activation of an option (such as GPC or Dissolution) does not change any project properties for existing projects without asking the user. Also reported as 53909.

 

CRI-601 Fixed in Empower 3.8.0:
INFEMP-6984 (CRI-601)
Previously, when you restored a backed up project, all available project options became enabled
in the restored project, including options not previously enabled in the project.
Now, this issue is fixed.
Also reported as PCS numbers 54503 and 48763.

id21162, EMP2LIC, EMP2OPT, EMP2SW, EMP3GC, EMP3LIC, EMP3OPT, EMP3SW, EMPGC, EMPGPC, EMPGPC, EMPLIC, EMPOWER2, EMPOWER3, EMPSW, GPCV2K, SUP