SYMPTOMS

  • When you clone a project, the project and its settings, along with the system policies set for that project (including GXP/ER/ES regulatory policies) exist in the clone projects, but not in the project's raw data or results.
  • If you change the system policies, it has no effect on previous projects and any cloned projects that were created before the policy changes. In other words, once you clone a project , it keeps the policy from the original project .Only brand new projects create take the new system policy.

 

ENVIRONMENT

  • Empower 3 Feature Release 3 Hotfix 1
  • System Policy

CAUSE

Working as designed.

FIX or WORKAROUND

PCS # 56194, opened on January 11, 2018, is an enhancement titled  "Project Cloning Usability Issues After System Policy Changes" to request the option to use the current 'New Project' system policies when cloning projects.

ADDITIONAL INFORMATION

 

id20179,