OBJECTIVE or GOAL
To power-on an ACQUITY QDa mass detector after a prolonged shutdown
ENVIRONMENT
- ACQUITY QDa Mass Detector
- Empower
- Empower Enterprise
- MassLynx
PROCEDURE
- Inspect the oil level on a performance pump.
- Confirm that the exhaust bottle is empty and exhaust lines are secured and not kinked.
- Confirm that the Stop Flow trigger is connected.
- Confirm that power cables, grounded Ethernet cables, and the performance pump relay box are connected properly.
- Confirm that the nitrogen line is connected and the supply is on.
- Power-on the host computer.
- View the following video for the remaining power-on sequences.
- Wait until Source Pressure test completes before opening MassLynx.
ADDITIONAL INFORMATION