OBJECTIVE or GOAL

Configure tubings on three-column selection valve as described in Installation Manual.

ENVIRONMENT

  • Alliance Series Column Heater Module
  • Alliance Series Column Heater/Cooler Module

PROCEDURE

The three-column selection valve is an eight-port, three-position valve that is preconfigured at the factory as follows:

Port 1 - Routed to the column (a 2.1 mm x 50 mm column is supplied)

Port 2 - Routed to waste

Port 3 - Routed through a restrictor bypass to the detector

ADDITIONAL INFORMATION

3posValve.JPG

id235601, 2690, 2690D, 2690DUPGD, 2690UP, 2695, 2695D, 2695DE, 2695DEB, 2695DUP, 2695E, 2695EB, 2695INERT, 2695UP, 2790XE, 2790XEUP, 2795E, 2795UP, 2795XE, A-10SSM, ALLCOLCLR, ALLCOLHTR, ALLCOLHTRB