Skip to main content
Waters

How to Calculate the Height of the Valley Point Between Two Fused Peaks - Tip79

Article number: 69292

OBJECTIVE or GOAL

Welcome back to Get Empowered! In the last Empower tip-of-the-week post for Empower CDS Software, we answered a reader-submitted question and learned how to quantitate impurities against the main component. (Tip #78)

(See the link at the bottom of our post to see previous questions, ask your own question, or to provide a tip of your own!)

In this week’s tip, I’ll answer a question as a follow-up to Tip #74 on using Empower’s System Suitability option to calculate the ratio of peak to valley height when there’s a valley between the chromatographic peaks.

Question: How can we calculate the height of the valley point between two fused peaks?

Another great question.

Let me show you how it is done.

ENVIRONMENT

  • Empower

PROCEDURE

  1. If we recall from Tip #74, the ratio of peak height to valley height is calculated as start p/v or end p/v. The height of the relatively big peak at 1.005 minutes ends at a valley point, so Empower Software reports the end p/v. The peak at 1.192 minutes starts at a valley point so Empower reports the start p/v.
69292-01.png
  1. If we solve for valley height, the calculation would be valley height = peak height/start p/v or peak height/end p/v.
69292-02.png
  1. This is a simple peak custom field in Empower. (You can make a similar one substituting end p/v.)
69292-03.png
  1. We see the result of the calculation in the peaks table in Review. The valley height is the same regardless of which calculation we use.
69292-04.png

 

It’s that easy!

ADDITIONAL INFORMATION

  1. We will do a series of Empower Tips on Custom Fields later this year… Stay tuned!
  2. This procedure can be followed using the QuickStart or Pro interface.

Not able to find a solution? Click here to request help.

  • Was this article helpful?