OBJECTIVE or GOAL

Add the "Next Injection Delay" field in an Empower report method.

ENVIRONMENT

  • Empower (all versions)

PROCEDURE

  1. From the Report Method, close to open the Report Method Editor.
  2. From the tree on the left-hand side, double-click Sample Set Method Group to add it to the report.
  3. Confirm that the Sample Set Table is selected in the Sample Set Method Properties.
  4. Click Apply > Save. 

ADDITIONAL INFORMATION

 