Empower Custom Field audit trail history is copied in full when using Copy to Project but not when using Save to Project - WKB258892
Article number: 258892
SYMPTOMS
- The full audit trail history for a Custom Field is copied when performing Copy to Project from within the Empower project containing the custom field
- The full audit trail history for a Custom Field is NOT copied when performing Save to Project from within the Empower project properties window
ENVIRONMENT
- Empower
CAUSE
This difference in behavior is documented in CRI-5808.
FIX or WORKAROUND
- If the full audit trail history is required, you must use the Copy to Project function from within the Empower project.
- If the full audit trail history is not required, you can leverage the Save to Project function from the Empower project properties window.
ADDITIONAL INFORMATION