OBJECTIVE or GOAL
Set project access parameters to correctly control user access.
ENVIRONMENT
- Empower 3
PROCEDURE
- Open "Configure the System".
- Find the project of interest, and then right-click on it and select "Properties".
- Select the "Access" tab.
- Choose the appropriate access option.
- If you have any questions regarding the access options, press the "F1" key on the keyboard to open a context-correct Help window.