Skip to main content
Waters

Can I enable full audit trail once the project is created in Empower ? - WKB1199

Article number: 1199

ENVIRONMENT

  • Empower

ANSWER

No, you cannot add Full Audit Trail (FAT) support after a project has been created.

ADDITIONAL INFORMATION

Full Audit Trail (FAT) support : Records all changes made to methods, results and samples for a project. This is based on system policies assigned. In the new project wizard, FAT is checked by default, see the screen shot below.

FAT .PNG

 

Empower Software Audit Trails and Logs White Paper 

id1199, EMP2LIC, EMP2OPT, EMP2SW, EMP3GC, EMP3LIC, EMP3OPT, EMP3SW, EMPGC, EMPGPC, EMPLIC, EMPOWER2, EMPOWER3, EMPSW, SUP